KOSS (Kindergarten on School Site)
2025 Project

Series
Education
Location
Echuca, Whitfield, Kerang & Mildura
Architect
Foreground Architecture
Images
Studio VP

KOSS (Kindergarten on School Site)
2025 Project

Series
Education
Location
Echuca, Whitfield, Kerang & Mildura
Architect
Foreground Architecture
Images
Studio VP

KOSS (Kindergarten on School Site)
2025 Project

Series
Education
Location
Echuca, Whitfield, Kerang & Mildura
Architect
Foreground Architecture
Images
Studio VP

Located on a school site, the KOSS (Kindergarten on School Site) 2025 kindergarten bundle is designed to make the transition into primary school smoother while also supporting families with convenience and connection.

With spacious undercover areas, excellent acoustics, and dedicated spaces for teachers to plan and collaborate, every detail has been thoughtfully designed to create the best learning environment possible.

 

 

KOSS Bundle 1, 2025 is a project involving the construction of four new kindergartens located across Mildura, Kerang, Echuca and Whitfield for the VSBA. Each kindergarten comprises a single-story main classroom building, outdoor learning areas, and car parks, all delivered within existing primary school sites.

Modular building allows site works and factory works to run in parallel. While site crews completed earthworks and footing in preparation for modular installation, factory teams progressed the modular building to approximately 70% completion before delivery to site, with the remaining works completed on site. This significantly reduced the overall construction program and minimised disruption to existing school operations.

Delivered through modular construction, the building was manufactured in our factory as permanent modules, then transported, assembled on site, and connected to essential services. Once complete, our team finished the outdoor learning areas and landscaping.

This approach delivers real benefits:

* Minimal disruption for kindergartens and their communities
* Quicker access to modern, high-quality learning environments
* Reduced construction time, costs, and safety risks

This project clearly demonstrates the efficiency, capabilities, and scalability of Prebuilt’s construction processes, enabling successful delivery of complex multi-site projects within an exceptionally tight timeframe. We are extremely proud of the outcome of this project. The project’s superintendent and our client, VSBA, have provided very positive feedback on both the delivery process and the final result.

The project was awarded to Prebuilt in late June 2024, and all four kindergartens were successfully completed and operational in time for the school start term 1 at the end of January 2025.

 